Common Information

The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.

Common information image for Pie Charts, Data Interpretation:1608-1


Common Information Question: 4/5

If the toll is to be collected through an outsourced agency by allowing a maximum 10% commission, how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4,910 crores?


Rs. 6213 crores


Rs. 5827 crores


Rs. 5316 crores


Rs. 5401 crores

 Hide Ans

Option(D) is correct

Amount permitted:

= (Funds required from Toll for projects of Phase II) + (10% of these funds)

= Rs. 4910 crores + Rs. (10% of 4910) crores

= Rs. (4910 + 491) crores

= Rs. 5401 crores.